North West
N4-14 Between Buffelspoort N4-13 km 2.9 and the P115-1(R24) Interchange N4-13 km 40
- Client: End Client : BAKWENA N1 N4 Toll - Our Client: Raubex
- Consulting Engineers: JG AFRIKA
- Subcontractor: Raubex
- Duration: 11 Months (Feb 2025 - Dec 2025)
- Contract Value: R 1.38 Million
Project Overview
Post Tensioning of the extension of bridge B2225 and B2227 for the dual carriageway on the N4.
Scope of Work
- Supply of Post Tensioning materials ie. tendon supports, sheathing, strand and anchorages, installation of strand and making of cast in dead en anchorages, tensioning and grouting of the post tensioning for both bridge B2225 and B2227.
Project Challenges
-
Assembly
Assembly of the dead end anchorages was very challenging because of to the confined space caused by the reinforcing that was required within the transverse beam where these anchorage needed to be positioned. -
Time constraints
Time was a challenge due to the disruption of the routes that community takes to commute to and through the town.
Execution Highlights
-
Smart Collaboration
Working hand in hand with Raubex lead to the successful installation of the dead end anchorages as well as ensured that both bridges were finished ahead of programme which made the community very happy.